VALHAL - instalation of water unit on existing drilling rig

Structural analysis and design of 6 skids to be mounted on Valhal drilling rig.

Analysis of lifting possibility using 55 tones maximum pay load crane, installed on platform.

SKANDITEK's arrangement was to ensure that entire water treatment plant is split into lifting-able skids.

Dynamic analysis has been conducted in order to see the behavior during transportation process.